+48 618 990 115
+48 602 155 661
wajm@pianobeton.pl

Cinema City

Renovation of a multi-story parking structure due to ongoing structural deterioration. The renovation involved replacing the concrete with PB 600 Foam Concrete. The structure’s levels were relie...

IKEA

Extension of the ceilings of the underground parking lot (second level of the parking lot), where a new hall, a utility road for delivery vehicles, and a parking lot for cars were created. PB 500 Foam...

Galeria Malta

Filling the load-bearing structures with regular concrete led to excessive settling of the structure. 5400 m² of the parking subbase was filled with PB 600 Foam Concrete, reducing the load by over 300...

Poznań – City Fire Department

Filling the ceiling structures, on which fire trucks operate, with PB 500 Foam Concrete. The Foam Concrete was covered with a 2x heat-welded membrane, and a 6 cm paver surface was laid on a sand-cemen...

Leningrad-type Residential Blocks

These buildings were erected economically without roof insulation. Low spaces and firewalls prevented access and the use of commonly used insulation materials. A grid of holes was drilled in the roof,...

Legnica – Knight Academy

These buildings were erected economically without roof insulation. Low spaces and firewalls prevented access and the use of commonly used insulation materials. A grid of holes was drilled in the roof,...

Pre-war Tenement Houses

Wrocław, Poznań, Legnica, Wałbrzych – thermal and acoustic insulation, as well as reinforcement and leveling of ceilings in pre-war tenement houses (1997). All buildings had wooden ceilings that requi...

Poznań National Museum

A building left in shell condition for 14 years awaiting construction continuation. When construction resumed, it was discovered that the level differences on the ceilings across the 7500 m² surface o...

Poznań Górecka Hall

Adaptation of an industrial facility for office and commercial purposes. The light structure of the newly created ceiling was filled with PB 600 Foam Concrete. See also: Subbase for floors   ...

Szczecin Shell Gas Station

On the site of a former river bend, foundations were twice attempted to be placed but sank into the muddy ground. When digging the site for fuel tanks, it was necessary to secure the excavations with ...

Statoil Gas Station Construction

A gas station was to be built on the site of a former sedimentation pond. The station building and refueling positions, the foundation of underground fuel tanks, and all access roads were built on PB ...

Elbląg – Water Pump Station Renovation

A slab foundation for the new pump station building and water tanks. The total thickness of PB 500 and PB 1000 Foam Concrete layers was 3 meters. See also: Industrial floor thickness   ...

Wolsztyn Road Overpass

Filling the abutment of the road overpass in Wolsztyn. The overpass has a load-bearing structure length of 167.8 meters, a roadway width of 7.0 meters, and sidewalks of 2 x 1.5 meters. It was necessar...

Piła Graphic Plants

A slab foundation measuring 80 x 4.5 x 1.2 meters for a new printing machine weighing several tons. A foundation was needed that could bear both static and dynamic loads, as the powerful guillotine cu...

Marriott Hotel Okęcie

Leveling the differences between the floors of individual levels over an area of 1300 m². See also: Foam Concrete price per m³ ...

Metropolitan Shopping Center

Filling the reinforced concrete ceiling structure above the underground garage. Roads, sidewalks, and flower beds were built on the surface. See also: Concrete industrial floor ...

Złote Tarasy Shopping Center

Extension of the ceilings of the underground parking, utility roads for delivery vehicles, and parking for cars. PB 500 Foam Concrete was used for the parking and PB 800 for the road under the asphalt...